    42 units, off Zinsco and onto their own PG&E meters.

    A multifamily brief for owners still running obsolete tenant metering. Zinsco equipment at the end of its life is a safety and insurance problem. Private submetering is a billing headache. This project fixed both in one scope.

    OAKLAND · 42 TENANT UNITS · ZINSCO METERING REMOVED · NEW 42-POSITION METER BANK · PG&E CONVERSION · $135,278 · 
    OAKLAND · 42 TENANT UNITS · ZINSCO METERING REMOVED · NEW 42-POSITION METER BANK · PG&E CONVERSION · $135,278 · 

    A 42-unit apartment building in Oakland was running its tenants on obsolete Zinsco metering equipment, mounted on the parking garage wall and billed through private submetering. GBS did a like-for-like replacement: removed the Zinsco tenant meters, installed a new PG&E-compliant 42-position meter bank and service-rated disconnect, and converted all 42 units to individual PG&E meters. GBS also ran the full PG&E application, including load calculations, the one-line diagram and equipment submittals, plus the city permit. The building's existing service, house meter and elevator meter stayed in place, which kept the scope and cost contained.

    Real results from a recent GBS client

    42-unit apartment building, Oakland

    42
    Tenant units converted to individual PG&E meters
    44
    Total meter positions on the service
    1
    New PG&E-compliant tenant meter bank
    1
    New service-rated disconnect, plus the old disconnect replaced
    0
    Changes to the existing service, house meter or elevator meter
    $135,278
    Total project price

    Why it matters

    →Zinsco is a red flag. Carriers and inspectors flag Zinsco equipment. Getting it off the wall protects insurability.
    →Tenants pay their own power. Converting from private submetering to individual PG&E meters takes the owner out of utility billing.
    →We handle PG&E. Load calculations, one-line diagram, equipment layout, submittals and follow-up are part of the job.
    →Like-for-like keeps cost down. Reusing the existing service and feeders avoids a full service upgrade.
    →Tenants stay in place. Shutdowns are planned with property management in advance to keep outage windows short.
    →One permit, one team. City permit, inspections and utility coordination run through a single contractor.

    What we did

    • Prepare and manage the PG&E service application to convert 42 privately submetered units to individual utility meters
    • Load calculations, one-line diagram, equipment layout and submittals for PG&E
    • City of Oakland electrical permit, plan review and inspections
    • Photograph and map every existing meter position before disconnection
    • Remove the Zinsco tenant metering and private submetering hardware
    • Install a new UL-listed, PG&E-compliant 42-position tenant meter bank
    • Install a new service-rated disconnect and replace the existing disconnect
    • Reconnect existing service and tenant feeders, with grounding and bonding for the new equipment
    • Label every new meter position, test, and prepare for PG&E's final meter set and energization

    What stayed in place

    Keeping the existing service configuration is what made this a contained, like-for-like project.

    • Existing overhead utility service and service room
    • Existing distribution box
    • Existing master meter, which becomes the house and common-area PG&E meter
    • Existing elevator meter
    • Existing feeders, raceway and service capacity

    How we delivered it

    1Site inspection and meter count
    2Fixed-price proposal issued
    3Agreement and deposit
    4PG&E application and city permit submitted
    5Meter schedule mapped and photographed
    6Shutdowns scheduled with property management
    7Zinsco removed, new meter bank and disconnect installed
    8City inspection
    9PG&E sets 42 new meters and energizes

    Figures reflect a specific completed GBS project. On any other building, PG&E controls its own review and energization schedule, and scope and price depend on utility and city requirements.

    Work with us

    Still on Zinsco or submeters?

    Tell us your unit count and what is on the wall. We will scope the replacement, run the PG&E process, and keep your tenants powered through it, the same way we did here.